Monday, March 10, 2014

LRT Line 2 East Extension Project

PROJECT DESCRIPTION
  • Extension of the existing LRT Line 2 by 4.19 km. eastward from the existing Santolan Station at Marcos Highway, terminating at the intersection of Marcos Highway and Sumulong Highway. 
  • With two (2) additional stations proposed: (1) Emerald Station in front of Robinsons Place Metro East in Cainta Rizal; and (2) Masinag Station at the Masinag Junction in Antipolo City. 

Proposed stations:
  • Emerald Station in front of Robinson’s Place Metro East in Cainta Rizal
  • Masinag Station at the Masinag Junction in Antipolo City

PROJECT LOCATION
Marcos Highway (Santolan, Pasig City to Masinag, Antipolo City)
PROJECT MAP


IMPLEMENTING AGENCY

  • Department of Transportation and Communications (DOTC)
  • Light Rail Transit Authority (LRTA)

CONTACT PERSON

  • Asec. Jaime Raphael C. Feliciano: +63 2 725 0013
  • Engr. Emil Galvante: +63 927 756 0621

CONSTRUCTION PERIOD

  • July 2014 to January 2016 (Civil Works)
  • November 2014 to June 2016 (Electro-Mechanical Works)

Bonifacio Global City to Ortigas Center Link Road Project (Phase I, IIA)

PROJECT DESCRIPTION

Phase I: 4-lane (2 lanes each direction) bridge with a length of 613.778 meters
Phase IIA: 4-lane (2 lanes each direction) bridge with a length of 497.165 meters
PROJECT LOCATION

Phase I: Sta. Monica - Lawton Bridge
Phase IIA: Lawton to Global City Viaduct
PROJECT MAP
IMPLEMENTING AGENCY
  • Department of Public Works and Highways (DPWH)
CONTACT PERSON
  • Director Virgilio C. Castillo, call +63 2 304 3658
CONSTRUCTION PERIOD
  • Phase I: July 2014 - June 2016
  • Phase IIA: July 2015 - June 2016

EDSA - Taft Ave. Flyover

PROJECT DESCRIPTION

  • 4-lane (2 lanes each direction) 3rd level flyover at the intersection of EDSA and Taft Ave.
  • Length: Northbound - 1,696 meters and Southbound - 1,046 meters

PROJECT LOCATION
Along EDSA from F.B. Harrison to Roxas Boulevard
PROJECT MAP
IMPLEMENTING AGENCY

  • Department of Public Works and Highways (DPWH)

CONTACT PERSON

  • Director Virgilio C. Castillo, call +63 2 304 3658

CONSTRUCTION PERIOD

  • January 2016 – June 2017

C.P. Garcia Ave. (C5) to McKinley Hill Ramp Proposal

PROJECT DESCRIPTION
  • A single lane on-ramp 5.3 km along the median of C5 road and terminates along McKinley Road at McKinley Hills.
  • Widening of Lawton Avenue to 8 lanes in anticipation of heavy traffic.
PROJECT LOCATION
Fort Bonifacio Global City, Makati City
PROJECT MAP
IMPLEMENTING AGENCY
  • Bases Conversion and Development Authority (BCDA)
CONTACT PERSON
  • Mr. Ray Apo +63 917 852 5414
  • Engr. Vergilio De Asis +63 2 421 2433 at +63 918 935 5266
PROJECT OWNER
  • Megaworld Corporation
CONTACT PERSON
  • Call Engr. Dick Montes at +63 917 872 0234 or +63 2 709 1111 loc. 110
CONSTRUCTION PERIOD
  • March 2014 to August 2014

South Super Highway - Repair / Rehabilitation / Improvement of Roads (Cluster A)

PROJECT DESCRIPTION

  • Pavement work (concrete re-blocking) intermittent section
  • Asphalt overlay
  • Sidewalk improvement (paving blocks)
  • Application of reflectorized pavement markings

PROJECT LOCATION
South Super Highway, Makati City, Metro Manila
PROJECT MAP:
IMPLEMENTING AGENCY:
  • Department of Public Works and Highways (DPWH) - NCR
CONTACT PERSON:
  • Director Reynaldo G. Tagudando +63 2 304 3700
CONTRACTOR:
  • Armando U. Khong Hun General Contractor, Inc.
CONSTRUCTION PERIOD:
  • January 2014 to June 2014

NAIA Expressway Phase 2

PROJECT DESCRIPTION
  • 7.15 km, 4-lane elevated expressway
  • Includes construction of toll plaza/6 on ramps and 6 off ramps (with 1 existing off-ramp) starting from Sales Avenue going to Andrews Avenue, Domestic Road, MIA Roads and ends at Macapagal Blvd./Pagcor Entertainment City
PROJECT LOCATION
  • Sales Road to Macapagal Avenue, Cities of Pasay and ParaƱaque
PROJECT MAP

IMPLEMENTING AGENCY

  • Department of Public Works and Highways (DPWH) - NCR
  • Public-Private Partnership Center of the Philippines (PPP Center)
  • Toll Regulatory Board (TRB)

CONTACT PERSON
  • Engr. Reynaldo G. Tagudando at +63 917 839 1584

PROJECT OWNER

  • San Miguel Corporation (SMC)

CONTRACTOR

  • D.M. Consunji Inc. (DMCI)

CONTACT PERSON

  • Engr. Dwight Taala +63 918 909 1774

CONSTRUCTION PERIOD

  • Phase 2A: January 2014 to May 2015
  • Phase 2B: April 2014 to October 2015