Tuesday, January 11, 2022

PNR NSCR MEYCAUAYAN UPDATE JAN.11, 2022

NLEX readies 'big-ticket' projects for 2022

A tollway company of the Pangilinan group is targeting to jumpstart the construction of two projects, coupled with the completion of the ₱23-billion NLEX Connector road this year.


"As the company ends 2021 with a positive note, we welcome 2022 with optimism as there are big-ticket projects that we will complete and commence this year," NLEX Corporation President and General Manager J. Luigi L. Bautista said in a statement Saturday.


While works on the NLEX C5 Link Mindanao Avenue-Quirino Highway Section were supposed to start in the second half of 2021, the company said the ₱2-billion project will be pursued this year.


The two-kilometer expressway section seeks to connect the Mindanao Avenue toll plaza and Quirino Highway in Novaliches, Quezon City. This is part of the 11.5-kilometer NLEX C5 Link between Mindanao Avenue, Quirino Highway, Regalado Avenue, Congressional Avenue and C.P. Garcia Avenue in Quezon City.


Once the whole NLEX C5 Link is operational, travel time between Mindanao Avenue and Commonwealth Avenue would be reduced from 45 minutes to just 10 minutes.


The company will also establish the third bridge at the Candaba Viaduct, expanding its capacity to four lanes per direction.


Meanwhile, the multibillion-peso NLEX Connector is expected to be finished this year, providing players in the logistics sector an option to avoid traffic congestion along EDSA and C5.


The 8-kilometer NLEX Connector will pass through 5th Avenue/C3 Road, EspaƱa Blvd. all the way to Sta. Mesa, Manila.


NLEX Corporation is a unit of the Metro Pacific Tollways Corporation, the toll road arm of the Metro Pacific Investments Corporation.


Aside from NLEX, the firm also operates the Subic-Clark-Tarlac Expressway.


https://cnnphilippines.com/business/2022/1/8/NLEX-readies-big-ticket-projects-for-2022.html

unified Grand Central station update today 1-11-22

NEW P2 BILLION EXPRESSWAY NG NLEX CORP UUMPISAHAN NA!!

LRT-1EXTENSION LATEST UPDATE, BACKARAN AREA NA ANG INSTALLATION NG GIRDE...

lrt 1 cavite extension update today january 11,2022

LRT1 CAVITE EXTENSION UPDATE COSTAL MALL NGAUN

LRT-1 Cavite extension is 62% complete — DOTr

The P64.9-billion Light Rail Transit (LRT)-1 Cavite Extension, which was delayed for two decades, is 61.60 percent complete as of December 2021, according to the Department of Transportation (DOTr).


The National Economic Development Authority (NEDA)- Investment Coordination Committee ( ICC) approved the LRT-1 Cavite Extension project in 2000 and Congress gave it a budget allocation for right-of-way acquisition in 2007.


However, as of June 2016, not a single post has been built, and not a single train has even been ordered, said DOTr. Worse, no required right-of-way has been certified “free and clear” by the project’s independent consultant, it added.


In 2019, after catching up on right-of-way acquisition, as well as addressing a number of unresolved issues and constraints, the DOTr, together with the Light Rail Transit Authority (LRTA) and Light Rail Manila Corporation (LRMC), started actual construction works for the project.


Once completed, this extension will reduce travel time between Baclaran and Bacoor, Cavite to 25 minutes, from one hour and 10 minutes.


It will also increase LRT-1’s capacity from 500,000 to 800,000 passengers daily.


In addition, the project generated more than 1,600 jobs during its construction phase, with more to be created once it becomes operational, said the DOTr.


https://mb.com.ph/2022/01/11/lrt-1-cavite-extension-is-62-complete-dotr/

24 poste or collums at 25 Girder nalang! #buildbuildbuildproject#Girder#...