NAIA Expressway Phase 2

PROJECT DESCRIPTION
  • 7.15 km, 4-lane elevated expressway
  • Includes construction of toll plaza/6 on ramps and 6 off ramps (with 1 existing off-ramp) starting from Sales Avenue going to Andrews Avenue, Domestic Road, MIA Roads and ends at Macapagal Blvd./Pagcor Entertainment City
PROJECT LOCATION
  • Sales Road to Macapagal Avenue, Cities of Pasay and ParaƱaque
PROJECT MAP

IMPLEMENTING AGENCY

  • Department of Public Works and Highways (DPWH) - NCR
  • Public-Private Partnership Center of the Philippines (PPP Center)
  • Toll Regulatory Board (TRB)

CONTACT PERSON
  • Engr. Reynaldo G. Tagudando at +63 917 839 1584

PROJECT OWNER

  • San Miguel Corporation (SMC)

CONTRACTOR

  • D.M. Consunji Inc. (DMCI)

CONTACT PERSON

  • Engr. Dwight Taala +63 918 909 1774

CONSTRUCTION PERIOD

  • Phase 2A: January 2014 to May 2015
  • Phase 2B: April 2014 to October 2015