The North–South Commuter Railway (NSCR), also known as the Clark–Calamba Railway, is a 148 km (92 mi) suburban passenger rail metro network being constructed in Luzon. "The NSCR will have 37 stations, spanning 29 local government units, and connecting 3 regions."
History
Background
Manila–Clark rapid railway system
A railway system running from Manila to Clark was set to be constructed in the 1990s, when then President Fidel Ramos signed a memorandum of agreement with Juan Carlos I of Spain for its construction in September 1994.
On August 24, 1995, North Luzon Railways was formed as a subsidiary of Bases Conversion and Development Authority. The NLRC then entered into an engineering, procurement and construction contract (EPRC) with the Spanish Railways Corporation on February 7, 1996, but the contract was later terminated on August 14, 1998, after the parties disagreed on the source of funding for the project.
In September 1999, the NEDA-ICC later approved the project, then known as the Manila–Clark rapid railway system, with Phase 1 covering the Caloocan–Calumpit segment and the source of funding to be the Obuchi Fund from the Japan Bank for International Cooperation. Right-of-way clearing and relocation of informal settlers began, but a presidential directive later halted the clearing activities, and the JBIC loan never happened.
NorthRail project
On September 14, 2002, a memorandum of understanding was signed by NorthRail and China National Machinery and Equipment Group (CNMEG) for the project. It was later approved as the NorthRail project on August 5, 2003, with the first phase covering Caloocan to Malolos segment. The project was estimated to cost around US$500 million, and the funding was to be covered by a US$400 million by the Export–Import Bank of China, and the rest to be shouldered by the government through BCDA and NLRC.
The project involved the upgrading of the existing single track to an elevated dual-track system, converting the rail gauge from narrow gauge to standard gauge, and linking Manila to Malolos City in Bulacan and further on to Angeles, Clark Special Economic Zone and the Clark International Airport. Preparatory construction began in early November 2006. Due to delays in the construction work, it was soon renegotiated with the Chinese government. Construction temporarily continued in January 2009 with the support of the North Luzon Railways Corporation.
Aquino administration
The NorthRail project was cancelled in March 2011, due to a series of delays, work stoppages, a controversy and anomalies with the foreign contractor. According to then DILG Secretary Mar Roxas, the Chinese were open to reconfiguring the project, and that he was meeting with his Chinese counterpart in a month's time. However, nothing materialized out of these talks.
The Philippine Supreme Court handed down in March 2012 a decision giving a lower court the go-signal to hear the case calling for the annulment of the allegedly overpriced contract. Instead of settling the entire US$184 million due in 2012, the Department of Finance will pay Export-Import Bank of China 4 equal payments of $46 million starting September 2012. National Economic and Development Authority (NEDA) Director-General Arsenio Balisacan said the 80-kilometer Northrail project would resume within the term of President Benigno Aquino III, but despite this announcement, the Northrail project was scrapped and replaced under different terms with different contractors.
The Department of Transportation and Communications previously examined reviving the project by commissioning a feasibility study by CPCS Transcom Ltd. of Canada. Part of the study examined having a Malolos–Tutuban–Calamba–Los Baños commuter line.
A feasibility study for the North–South Commuter Railway was still ongoing when the NEDA approved the dream plan in 2014.
Development
In November 2017, DOTr, BCDA, and North Luzon Railways reached an out-of-court settlement with Sinomach, resolving the five-year dispute. The new name for the project was announced by Department of Transportation Secretary Arthur Tugade on June 25, 2017 with a ceremony in which the first 5 stations were given their location markers.
The Japan International Cooperation Agency will finance NSCR North 1, while the remaining sections will be co-financed by the Asian Development Bank.
Construction
Construction of the NSCR will be built into three phases and will be divided into two lines.
NSCR North (Tutuban–Malolos–Clark)
NSCR North, also known as PNR Clark, was divided into two phases. NSCR North 1 involves the 38 km (24 mi) Tutuban-Malolos segment, while NSCR North 2 involves the 53 km (33 mi) Malolos–Clark Railway. The 91-kilometer railway line, when fully completed, will run from Tutuban Station in Manila to New Clark City (NCC), passing through Clark International Airport (CIA).
Pre-construction work such as clearing of the right of way was started in January 2018. The groundbreaking and construction from Tutuban to Malolos started on February 15, 2019. The contract for the construction of PNR North 1 was awarded to the Filipino-Japanese consortium of DMCI Holdings and Taisei Corporation on May 21, 2019.
On the other hand, the first three contracts for the construction of NSCR North 2 had been opened in August 2019. A record 11 firms from various ADB member countries participated in the bid.
NSCR North 1 is expected to be completed by 2021, while NSCR North 2 is slated for operation 2 years later by 2023.
NSCR South (Solis–Calamba)
The existing Metro Commuter Line will be reconstructed as an elevated electrified standard-gauge line. The 72 km railway will run from Solis, Manila to Calamba, Laguna. It is expected to be completed by 2025.
Future
A study originally published in 2014 by the Japan International Cooperation Agency, the National Economic and Development Authority, and ALMEC Corporation revealed the master plan for the NSCR. The entire line will run between Tarlac City and Batangas City. If realized, the total system length will be around 220 kilometers.
- MCRP Civil Packages: Total of 5 civil packages, 5 elevated stations and 1 underground station
- NSRP-South Civil Packages: Total of 8 civil packages 18 elevated stations
- E&M Packages: Total of 10 systems
- Commuter Rolling Stock: 38 Commuter Trainsets
- Depots: Mabalacat (North) and Banlic (South)
Regions
- Central Luzon
- Metro Manila
- CALABARZON
- Capas
- Bamban
- Mabalacat
- Angeles
- San Fernando
- Santo Tomas
- Minalin
- Apalit
- Calumpit
- Malolos
- Guiguinto
- Balagtas
- Bocaue
- Marilao
- Meycauayan
- Valenzuela
- Malabon
- Caloocan
- Manila
- Makati
- Taguig
- Parañaque
- Muntinlupa
- San Pedro
- Binan
- Santa Rosa
- Cabuyao
- Calamba
- Los Banos
- New Clark City
- Capas
- Bamban
- Clark International Airport
- Clark
- Balibago
- Angeles
- Tablante
- Calulut
- San Fernando
- Santo Tomas
- Macaluc
- Apalit
- Sulipan
- Calumpit Norte
- Calumpit
- Bagbag
- Malolos
- Cofradia
- Dakila
- Bagong Bayan
- Bulacan Sports Complex
- Bulacan Industrial City
- Tabang
- Guiguinto
- Bigaa
- Lomboy
- Bunio
- Bocaue
- Saluysoy
- SM City Marilao
- Saog
- ITM
- Meycauayan College
- Meycauayan
- Polo
- Dalandanan
- Malinta
- Tinajeros (Goldendale Business Park)
- Governor Pascual
- Caloocan-Sangandaan
- Caloocan
- Horace Higgins Hall
- C3
- Hermosa
- Solis
- Tutuban
- Tayuman
- Mayhaligue
- Blumentritt
- Laong-Laan
- España
- Legarda
- Sampaloc
- Santa Mesa
- Pandacan
- Paco
- San Andres
- Vito Cruz
- Dela Rosa
- Pasay Road
- EDSA
- Nichols
- FTI
- Bicutan
- Sucat
- Buli
- Alabang
- Muntinlupa
- Tunasan
- San Pedro
- Pacita Complex
- Golden City 1
- Biñan
- Santa Rosa
- Golden City 2
- Cabuyao
- Mamatid
- Banlic
- Calamba
- Bucal
- Pansol
- Masile
- Los Baños
- UP Los Baños
- IRRI