Thursday, August 9, 2018

Right-of-way problems threaten to delay MRT 7 project

Decongesting traffic in northern Manila faces yet another hurdle as completion of the P67-billion Metro Rail Transit (MRT) 7 is being hampered by right-of-way (ROW) issues involving a planned train depot in Bulacan province, the Department of Transportation (DOTr) said on Tuesday.

Goddes Libiran, DOTr communications director, said the deparment had asked the Office of the Solicitor General (OSG) to file a petition for certiorari over a recent Malolos court ruling raising the zonal valuation of a 33-hectare lot in San Jose del Monte by nearly 900 percent.

In November, the DOTr filed an expropriations case in the Malolos regional trial court to acquire the land for the 22-kilometer MRT 7 project which would connect Quezon City to Bulacan province.

But on Feb. 15, Libiran said Judge Felizardo Montero issued an order granting writ of possession, provided that the government pay the property owner P1,800 per square meter based on a proposed Bureau of Internal Revenue (BIR) zonal valuation that was not yet in force.

The current and actual BIR valuation was P200 per sq m, also the basis for the DOTr’s initial deposit of P67 million for the 33-hectare land, Libiran added.

A July 2 letter from San Miguel Corp. (SMC), which is in charge of the project, said the new computation would cause the deposit to balloon to around P598 million, or nearly 56 percent of the DOTr’s total ROW budget for the project.

Libiran said that SMC would not be able to complete MRT 7 if the DOTr could not resolve the ROW dispute.

This could also push back the project’s completion from 2020 to 2021—a significant delay given the magnitude of the Metro traffic problem.

The OSG asked the court for a 60-day extension on Aug. 1.

Read more: http://newsinfo.inquirer.net/1018815/right-of-way-problems-threaten-to-delay-mrt-7-project#ixzz5NeImRxzp
Follow us: @inquirerdotnet on Twitter | inquirerdotnet on Facebook

Right-of-way issues may delay MRT7 completion

Transportation officials are appealing the 800% raise in zonal valuation of the 33-hectare lot intended for the Metro Rail Transit Line 7 depot

The completion of the long-delayed Metro Rail Transit Line 7 (MRT7) project could further be hampered due to right-of-way (ROW) acquisition issues.

The Department of Transportation (DOTr) is appealing the Malolos Regional Trial Court Branch 11 decision raising the zonal valuation of the 33-hectare lot in San Jose del Monte, Bulacan intended to be the MRT7 depot.

In a phone interview, DOTr Communications Director Goddes Hope Libiran told Rappler that the department sought the help of the Office of the Solicitor General (OSG) to file a petition for certiorari at the Court of Appeals (CA).

From the original zonal valuation of P200 per square meter, the May ruling raised it to P1,800 per square meter – a whopping 800% increase. (READ: A long, winding road for better Metro Manila transport)

"If the writ of possession is issued later within the year, it could delay the completion of the project to 2021 instead of 2020," Libiran said in a mix of English and Filipino.

What happened? According to Libiran, they filed an expropriation case back in November 2017. Concessionaire San Miguel Corporation later on paid P67 million to acquire the land.

Under Republic Act No. 10752 or the Right-of-Way Act, the court should issue a writ of possession to the implementing agency within 7 days after the payment has been made.

No writ of possession was released to the DOTr and Judge Felizardo Montero instead asked the OSG to present evidence that the current zonal value of the property is at P200 per square meter.

Montero also said the writ of possession would be released when the P1,800 per square meter would be paid. Libiran said they filed a motion for reconsideration then.

"They asked the OSG to withdraw the motion for reconsideration because there was an approval [to raise the zonal valuation]. If they didn't delay the issuance of the writ of possession, we could have acquired the property prior to the approval of the raise," she said.




Next steps? The DOTr had asked on August 1 for an extension of 60 days to file the appeal at the CA.

If the CA does not rule in the department's favor, the MRT7 completion might be stalled again.

"If we pay roughly P598 million, we would already take 56% of the ROW budget for this year. How about other projects? We might have to seek the approval of NEDA again which would further delay the project," Libiran said.

She also said 45 of 108 train cars for the railway system are ready to be imported, pending the completion of the depot.

After previous delays, construction of the project had begun in April 2016.

The 23-kilometer railway system, which will run from North Avenue in Quezon City to San Jose del Monte City in Bulacan, will have 14 train stations that will take 30 minutes to travel end-to-end.

It will be connected to the existing Metro Rail Transit Line 3 (MRT3) and Light Rail Transit Line 1 (LRT1) via a common station along EDSA.