Monday, July 26, 2021

ADB $1.75-B loan for south rail project up for board approval

THE ASIAN Development Bank (ADB) said it is scheduled to approve a $1.75-billion loan for the South Commuter Railway project, which will connect Tondo, Manila and Calamba, Laguna, by the fourth quarter.


“The Philippine government held successful biddings for civil works contracts for a combined 40.5 kilometers (km) of viaduct structures for the South Commuter Railway Project, a major flagship project the ADB is preparing for funding support for consideration by its Board of Directors in the fourth quarter of this year,” the bank said in a statement Monday.


The loan is the biggest ADB financing package for the Philippines this year.


The P344.6-billion south railway system is part of the flagship 147-kilometer North-South Commuter Railway System project, which will link Pampanga, Manila and Laguna by 2025.


It was also poised to become the country’s first airport express system since it will be connected to Clark International Airport in Pampanga.


During the bidding last week, the South Commuter Railway project, also referred to as the Philippine National Railways (PNR) project, attracted 34 bids from 17 international and six local companies wanting to take part in the construction of the railway system.


Transportation Secretary Arthur P. Tugade said the bidding attracted a “record-breaking turnout” from both Philippine and foreign companies. The government is planning to offer more contract packages for the project’s electromechanical systems and airport express train cars this quarter.


“We congratulate the Department of Transportation and PNR on the successful bidding turnout, which reflects robust local and global interest and confidence in the Philippines’ ‘Build, Build, Build’ infrastructure development program and for a strong post-pandemic economic recovery,” ADB Philippine Country Director Kelly Bird said in the statement.


“We are pleased to partner with the Philippine government in this transformative project that will have substantial multiplier effects on the economy and regional development,” he added.


The bank is planning to lend the government $3.9 billion this year.


The south rail transport system is also linked to another ADB-funded project, the 53-km Malolos-Clark Railway Project, for which the bank extended $2.75 billion worth of financing in May 2019.


The North-South Commuter Railway line was co-financed by the ADB and Japan International Cooperation Agency (JICA). It will have 37 stations and 464 train cars or 58 trains sets, which includes airport express trains.


The system, with capacity of up to 1 million passengers daily, is expected to cut the travel time between Clark airport and Calamba, Laguna to 1.5 hours, from four hours currently.


In 2019, JICA also lent the government P80 billion for the first phase of the North-South Commuter Railway system. — Beatrice M. Laforga


https://www.bworldonline.com/adb-1-75-b-loan-for-south-rail-project-up-for-board-approval/

ADB to finance South commuter railway

The government held successful biddings for civil works contracts for a combined 40.5 kilometers of viaduct structures for the South Commuter Railway Project, a major flagship project the Asian Development Bank is preparing for funding support for consideration by its board of directors in the fourth quarter.


The submission and opening of bids on July 14 to 15, which included contracts for elevated stations and a 22-hectare train depot, attracted a record 34 bids from a total of 23 local and international engineering and construction firms. ADB provided advisory services on the bidding process under its Infrastructure Preparation and Innovation Facility.        


“We congratulate the Department of Transportation and the Philippine National Railways (PNR) on the successful bidding turnout, which reflects robust local and global interest and confidence in the Philippines’ ‘Build, Build, Build’ infrastructure development program and for a strong post-pandemic economic recovery,” said ADB Philippines country director Kelly Bird.


The South Commuter Railway Project, also called PNR-Calamba, is a key component of the 147-km North–South Commuter Railway system that will reshape the country’s mass transportation network. It will cut travel time from the Clark International Airport in Pampanga province north of Metro Manila to Calamba City in the south from more than 4 hours to just 1.5 hours. The entire railway system is expected to carry up to 1 million passengers daily.


The project is included in ADB’s country operations business plan for the Philippines. It links to another ADB-funded railway, the Malolos–Clark Railway Project approved by ADB in May 2019, a modern, elevated railway line that will connect northern provinces to Metro Manila.


It will feature the country’s first airport express train, with the railway connecting to Clark International Airport. Five civil works contracts worth $2.5 billion under the project were awarded in 2020 and are now under implementation.


“We are pleased to partner with the Philippine government in this transformative project that will have substantial multiplier effects on the economy and regional development,” Bird said.


ADB said it is committed to achieving a prosperous, inclusive, resilient, and sustainable Asia and the Pacific, while sustaining its efforts to eradicate extreme poverty. Established in 1966, it is owned by 68 members—49 from the region.


https://manilastandard.net/mobile/article/360732

ADB prepares funding support for PNR Calamba

The Asian Development Bank (ADB) is preparing its funding support for the P345-billion Philippine National Railways’ (PNR) Calamba project.


In a statement, the Manila-based multilateral financial institution said that funding for the 40.5 kilometer viaduct structures of PNR Calamba, also called South Commuter Railway Project, is up for “consideration” by the ADB Board in the fourth-quarter.


“We are pleased to partner with the Philippine government in this transformative project that will have substantial multiplier effects on the economy and regional development,” Kelly Bird, ADB Philippines country director said Monday, July 26.


PNR-Calamba is a key component of the 147-kilometer North–South Commuter Railway (NSCR) system that aims to cut travel time from Clark International Airport in Pampanga to Calamba City from more than four hours to just 1.5 hours.


The NSCR system is expected to carry up to one million passengers daily.


Last July 14 to 15, the Department of Transportation (DOTr) held the submission and opening of bids for the civil work contracts that include elevated stations, viaduct structures, and a 22-hectare train depot for PNR Calamba.


A record 34 bids from 23 local and international engineering and construction companies vied for contract packages, DOTr said.


Six local players participated in the bidding that include D.M. Consunji Inc., EEI Corp., First Balfour Inc., Megawide Construction Corp., Prime Metro BMD Corp. and Santa Clara International Corp.


Seventeen foreign companies, meanwhile, submitted bids. These include Japan’s Sumitomo Mitsui Construction Co., South Korea’s Hyundai Engineering Construction Co., Spain’s Acciona S.A. and China Construction First Group Corp.


Moreover, Chun Wo Construction (Hongkong), Leighton Contractors (Asia) Ltd. (Hongkong), DL Engineering and Construction Co. Ltd. (South Korea), Dong-ah Geological Engineering Co. Ltd. (South Korea), and GS Engineering and Construction Corp. (South Korea) also participated.


In addition, Lotte Engineering and Construction Co., Ltd. (South Korea), POSCO Engineering and Construction (South Korea), and Samsung Construction and Trading Corp. (South Korea).


The remaining foreign bidders were PT Adhi Karya (Persero) Tbk (Indonesia), PT PP (Persero) Tbk (Indonesia), PT Wijaya Karya (Persero) Tbk (Indonesia), Gülermak Ağır Sanayi İnşaat ve Taahhüt A.Ş. (Turkey) and Italian-Thai Development Public Company Ltd. (Thailand).


“We congratulate the DOTr and the PNR on the successful bidding turnout, which reflects robust local and global interest and confidence in the Philippines’ Build, Build, Build infrastructure development program and for a strong post-pandemic economic recovery,” Bird said.


PNR Calamba is included in ADB’s country operations business plan for the Philippines.


It is also linked to another ADB-funded railway, the Malolos-Clark Railway that features the country’s first airport express train, with the railway connecting to Clark International Airport.


https://mb.com.ph/2021/07/26/adb-prepares-funding-support-for-pnr-calamba/

‘Build, Build, Build:’ Hits vs hype

When President Rodrigo Duterte addressed the nation in 2017, he promised that the following years would be the “golden age of infrastructure” in the Philippines that would “enhance our mobility and connectivity.”


Filipinos were introduced to “Build, Build, Build” (BBB), the package of flagship infrastructure projects that the President vowed to deliver before leaving office. Pouring massive resources into the development of the archipelago’s network of highways, farm-to-market roads, bridges, railways, seaports and airports made sense as they would create jobs and enhance countryside development.


But how many of these projects had been “Built, Built, Built” with less than a year left before Duterte steps down from Malacañang?


MINDANAO


Still waiting for bidders


In the president’s home region, the promised Mindanao Railway that aims to link the main southern island’s major cities and urban centers, has yet to leave the station more than four years after its launch.


Transportation Secretary Arthur Tugade said the government was still waiting for the shortlist of bidders for its design and construction from the Chinese government to start the first phase of the project that would connect Digos City to the cities of Davao and Panabo.


Tugade said his department was “quietly” working to make this dream a reality. “This will push through,” he recently told the Davao City Disaster Radio, referring to the P81.69-billion project funded by an official development assistance from China.


“Once we receive that shortlist, we will immediately start the procurement and construction, which we hope will be this year,” he said.


55-km bike lanes


One of the 11 “high-impact” projects of the Department of Public Works and Highways (DPWH) in the Davao region caught everyone’s attention for its early completion—a 55-km network of bicycle lanes that connects Metro Davao’s residential areas to its main hubs. It was started on Feb. 21 this year and was finished in June.


Tugade said the P150-million project would help the public cope with the reduced passenger load of public transportation during the pandemic.


GenSan airport


Not too far from Davao, the P1.09-billion upgrade of the General Santos City airport is now 96-percent complete and will be finished this year, making it capable of servicing inbound night flights, according to Joel Gavina, city manager of Civil Aviation Authority of the Philippines.


The upgrade includes a boarding bridge so that passengers and crew no longer have to walk under the sun or the rain, which they had to endure over the past 25 years, to get to and from their planes.


“You can be proud of the airport’s facelift,” Gavina told the Inquirer in a phone interview.


VISAYAS


1 done out of 15


The Bohol-Panglao International Airport is the only completed BBB project of the 15 in the Visayas listed on the website of the National Economic and Development Authority (Neda).


The P7.8-billion project began in 2015 during the administration of the late President Benigno Aquino III. It started operation on Nov. 27, 2018.


Three of six major infrastructures classified as “in the process of completion” were started by the previous administration: the Jalaur River Multipurpose Project (JRMP) in Calinog town in Iloilo, the Cebu Bus Rapid Transit (BRT) system, and the Bacolod-Negros Occidental Economic Highway.


Work on the three others—the P1.94-billion Boracay Circumferential Road, the Samar Pacific Coastal Road, and the New Panglao-Tagbilaran Offshore Bridge Connector — began after Mr. Duterte took office.


Yet to start


The following projects have yet to start: the fourth Cebu-Mactan Bridge and Coastal Road Construction Project; Cebu Monorail System; the New Cebu International Container Port (NCICP); Bacolod-Silay International Airport expansion; Iloilo ports development; Panay-Guimaras-Negros bridge; Kalibo International Airport development project; and Iloilo International Airport expansion.


The P11.2-billion JRMP Phase II in Iloilo’s Calinog town was 37.83 percent complete as of March 31.


Considered the biggest ongoing project in the region and the biggest dam outside Luzon, the JRMP is set to be completed in 2023, according to the National Irrigation Administration.


The Panay-Guimaras-Negros bridge is back to the drawing board after its funding source, the Chinese government, backed out.


The International Container Terminal Services Inc. (ICTSI) has submitted an unsolicited proposal to the Philippine Ports Authority to develop the Iloilo Commercial Port Complex and the Port of Dumangas in Iloilo. The ICTSI invested at least P8.7 billion for these projects.  


The upgrade of the Kalibo International Airport and the expansion of the Iloilo International Airport are awaiting approval from several government agencies.


The NCICP in Consolacion town is expected to break ground on Aug. 16. The P9.96-billion project will be financed through a $172.64-million loan agreement between the Philippines and the Export-Import Bank of Korea.


The government will start partial operations of its first BRT system in Cebu by December. The P16.3-billion World Bank-funded project will be fully operational in 2023.


The Cebu-Cordova Bridge, known as the Cebu-Cordova Link Expressway, or third bridge, is 80 percent complete as of July. Once finished, the 8-km bridge, which connects Cebu with Mactan Island, will be the longest in the Philippines.


Finished by 2024


The Negros highway, which will pass by the Bacolod-Silay Airport, will provide an alternate route from southern to northern Negros Occidental.


The project involves the opening, concreting, and widening of 38.8 km of roads, construction of 10 new bridges, slope protection works, and improvement of an existing 11.15-km road and six bridges, said DPWH-Western Visayas director Lea Delfinado.


It is set to be completed in December 2024, eight years after construction started in March 2016.


The Samar coastal road is 52.260 percent complete as of June 2021, according to the Northern Samar Second District Engineering Office (NSSDEO).


The P997.5-million project is funded through a loan from South Korea’s Korean Economic Development Cooperation Fund.


Engineer Raul Nuqui of the Unified Project Management Cluster of NSSDEO said bad weather, shortage of construction materials, lack of manpower, and COVID-19 restrictions had hampered construction work.  


LUZON


Bicol International Airport


In Luzon, the Bicol International Airport (BIA) in Albay, which three presidents had listed as a flagship project, is set to be opened initially for domestic flights in December.


The BIA in Daraga town is envisioned as an international air hub that is projected to spur economic growth and boost tourism in the region.


Neda Bicol director Agnes Espinas Tolentino said 83 percent of civil works and 87 percent of overall physical work at the airport had been completed as of June.


The government has spent P3.9 billion on the BIA since 2009.


SLEX extension


The extension of the South Luzon Expressway from Santo Tomas, Batangas, to Lucena City in Quezon province is ongoing.


In Central Luzon and the Ilocos regions, the Duterte administration’s big-ticket infrastructure projects involve railways and the expansion of expressways.


A P50-billion 71-km Subic-Clark railway will be funded by Chinese companies. It is a component of the PNR Luzon System Development Framework that will provide freight service between Subic Bay Freeport and Clark Freeport, and link Subic Port to Clark International Airport and other major economic hubs in Central Luzon, especially New Clark City.


In January this year, the Philippines and China signed the project’s commercial contract, making it the “highest funded government-to-government project between the two countries.”


Clark-Bulacan-Manila link


Aside from the Subic-Clark Railway, a rail system will connect Clark to the City of Malolos in Bulacan and Manila.


The PNR Clark Phase 1 from Tutuban in Manila to Malolos was 46.68 percent complete as of June, according to Tugade.  


This 39-km segment, to be finished in 2024, is part of the North-South Commuter Railway project conceptualized during the Ramos administration.


The proposed P175.7 billion Bataan-Cavite Interlink Bridge is expected to spur development in Bataan province and other parts of Central Luzon as well as neighboring cities in Metro Manila.


Bataan Gov. Albert Garcia told the Inquirer that the more than 32-km bridge would shorten the travel time between the two provinces from three hours to 30 minutes.


“This is a significant project that will benefit Bataan and Central Luzon because this will pave the way for more businesses to flourish,” said Garcia.


The DPWH opened this month portions of the 30-km Central Luzon Link Expressway between Tarlac City and Nueva Ecija.


In Northern Luzon, the last segment of the 88-km Tarlac-Pangasinan-La Union Expressway (TPLEx) was opened to motorists in July last year.


The expansion of TPLEx, a toll road operated by San Miguel Corp., was aimed at cutting an hour off the four-hour trip from Manila to Baguio City and other northern destinations.


—REPORTS FROM GERMELINA LACORTE, BONG SARMIENTO, NESTOR BURGOS JR., JOEY GABIETA, LEO UDTOHAN, CARLA GOMEZ, ADOR VINCENT MAYOL, MAR ARGUELLES, JOANNA ROSE AGLIBOT, TONETTE OREJAS, GREG REFRACCION AND YOLANDA SOTELO