Project Status:
- N. Domingo Bridge also known as Pinaglabanan Bridge (Old Sta. Mesa Bridge) opened to the public on March 11, 2020
- Sevilla Bridge opened to the public on August 17, 2020
- Quirino South Bound On Ramp (beginning at Concordia straight to Buendia, Skyway Stage 1) was completed and opened to traffic on July 22, 2019
- Quirino North Bound East Off Ramp (along Osmeña Highway and terminate before Quirino Ave.) was completed and opened to traffic on December 23, 2019
- Work stoppage from March 16, 2020 to May 15, 2020 due to ECQ in Luzon
- Concreting works for the entire main viaduct slabs including the reconstruction of fire affected structures in Sec. 2B was completed on October 11, 2020
- Ongoing construction of Section 1 Buendia-Quirino-Nagtahan, 91.08% accomplishment
- Ongoing construction of Section 2A Nagtahan-Tomas Claudio, 93.96% accomplishment
- Construction of Section 2A Tomas Claudio – PUP Sta. Mesa, 0% accomplishment
- Ongoing construction of Section 2B Tomas Claudio-Ramon Magsaysay Avenue, 94.77% accomplishment
- Ongoing construction of Section 3 Ramon Magsaysay to Quezon Ave., 97.35% accomplishment
- Ongoing construction of Section 4 Quezon Avenue – Balintawak, Q.C., 78.28% accomplishment
- Ongoing construction of Section 5 Balintawak, Q.C. – NLEX Footbridge, 92.70% accomplishment
- Overall construction accomplishment 92.17% (excluding Section 2A’)
- Construction of ramps accomplishment 50.35% (4 ramps completed, 19 ramps ongoing construction, 6 ramps under planning – total: 29 ramps)
Ramps completed:
- RN1 – Northbound On-Ramp Buendia (Open to traffic)
- RS1 – Southbound Off-Ramp Buendia (Open to traffic)
- RN2 – Northbound Off-Ramp Osmeña~Quirino (Open to traffic)
- RS3 – Southbound On-Ramp Plaza Dilao (Open to traffic)
Ramps ongoing construction:
- RN2 – Northbound On-Ramp Quirino
- RS3 – Southbound Off-Ramp Plaza Dilao
- RS3’ – Southbound Off-Ramp United Nations
- RN3 – Northbound Off-Ramp Nagtahan
- RN3-1 – Northbound On-Ramp Nagtahan
- RS3-1 – Southbound Off-Ramp Nagtahan
- RN5 – Northbound On-Ramp Araneta
- RS5 – Southbound Off-Ramp Araneta
- RN6 – Northbound Off-Ramp Quezon Ave.
- RS6 – Southbound Off-Ramp Quezon Ave.
- RN7 – Northbound On-Ramp Talayan-Quezon Ave.
- RS7 – Southbound Off-Ramp Talayan-Quezon Ave. (completed except asphalt overlay)
- RN8 – Northbound Off-Ramp to C3
- RS8 – Southbound On-Ramp from C3
- RS8-1 – Southbound Off-Ramp to C3
- RS9 – Southbound On-Ramp Balintawak/Ayala (with utilities obstruction)
- RN9 – Northbound Off-Ramp Balintawak/Ayala (with utilities obstruction)
- RN10 – Northbound Off-Ramp NLEX
- RS10 – Southbound On-Ramp NLEX
Ramps under planning:
- RS2 – Southbound On-Ramp Quirino-Osmeña
- RN2 – Northbound Off-Ramp Osmeña-Roxas Blvd.
- RN4 – Northbound On-Ramp Pandacan
- RS4 – Southbound Off-Ramp Pandacan
- RN4’ – Northbound Off-Ramp Valenzuela Street
- RS4’ – Southbound Off-Ramp Valenzuela Street
Overall Right-of-Way accomplishment (Site Possession) 95%(excluding Section 2A’), 231 out of 350 lots to be acquired with Permit to Enter