Saturday, November 14, 2020

Metro Manila Skyway

Project Status: 


  • N. Domingo Bridge also known as Pinaglabanan Bridge (Old Sta. Mesa Bridge) opened to the public on March 11, 2020
  • Sevilla Bridge opened to the public on August 17, 2020
  • Quirino South Bound On Ramp (beginning at Concordia straight to Buendia, Skyway Stage 1) was completed and opened to traffic on July 22, 2019
  • Quirino North Bound East Off Ramp (along Osmeña Highway and terminate before Quirino Ave.) was completed and opened to traffic on December 23, 2019
  • Work stoppage from March 16, 2020 to May 15, 2020 due to ECQ in Luzon
  • Concreting works for the entire main viaduct slabs including the reconstruction of fire affected structures in Sec. 2B was completed on October 11, 2020
  • Ongoing construction of Section 1 Buendia-Quirino-Nagtahan, 91.08% accomplishment
  • Ongoing construction of Section 2A Nagtahan-Tomas Claudio, 93.96% accomplishment
  • Construction of Section 2A Tomas Claudio – PUP Sta. Mesa, 0% accomplishment
  • Ongoing construction of Section 2B Tomas Claudio-Ramon Magsaysay Avenue, 94.77% accomplishment
  • Ongoing construction of Section 3 Ramon Magsaysay to Quezon Ave., 97.35% accomplishment
  • Ongoing construction of Section 4 Quezon Avenue – Balintawak, Q.C., 78.28% accomplishment
  • Ongoing construction of Section 5 Balintawak, Q.C. – NLEX Footbridge, 92.70% accomplishment
  • Overall construction accomplishment 92.17% (excluding Section 2A’)
  • Construction of ramps accomplishment 50.35% (4 ramps completed, 19 ramps ongoing construction, 6 ramps under planning – total: 29 ramps)


Ramps completed:


  • RN1 – Northbound On-Ramp Buendia (Open to traffic)
  • RS1 – Southbound Off-Ramp Buendia (Open to traffic)
  • RN2 – Northbound Off-Ramp Osmeña~Quirino (Open to traffic)
  • RS3 – Southbound On-Ramp Plaza Dilao (Open to traffic)


Ramps ongoing construction:

  • RN2 – Northbound On-Ramp Quirino
  • RS3 – Southbound Off-Ramp Plaza Dilao
  • RS3’ – Southbound Off-Ramp United Nations
  • RN3 – Northbound Off-Ramp Nagtahan
  • RN3-1 – Northbound On-Ramp Nagtahan
  • RS3-1 – Southbound Off-Ramp Nagtahan
  • RN5 – Northbound On-Ramp Araneta
  • RS5 – Southbound Off-Ramp Araneta
  • RN6 – Northbound Off-Ramp Quezon Ave.
  • RS6 – Southbound Off-Ramp Quezon Ave.
  • RN7 – Northbound On-Ramp Talayan-Quezon Ave.
  • RS7 – Southbound Off-Ramp Talayan-Quezon Ave. (completed except asphalt overlay)
  • RN8 – Northbound Off-Ramp to C3
  • RS8 – Southbound On-Ramp from C3
  • RS8-1 – Southbound Off-Ramp to C3
  • RS9 – Southbound On-Ramp Balintawak/Ayala (with utilities obstruction)
  • RN9 – Northbound Off-Ramp Balintawak/Ayala (with utilities obstruction)
  • RN10 – Northbound Off-Ramp NLEX
  • RS10 – Southbound On-Ramp NLEX


Ramps under planning:


  • RS2 – Southbound On-Ramp Quirino-Osmeña
  • RN2 – Northbound Off-Ramp Osmeña-Roxas Blvd.
  • RN4 – Northbound On-Ramp Pandacan
  • RS4 – Southbound Off-Ramp Pandacan
  • RN4’ – Northbound Off-Ramp Valenzuela Street
  • RS4’ – Southbound Off-Ramp Valenzuela Street


Overall Right-of-Way accomplishment (Site Possession) 95%(excluding Section 2A’), 231 out of 350 lots to be acquired with Permit to Enter

NLEX SLEX CONNECTOR ROAD 11-10-20