PROJECT DESCRIPTION
Buendia, Makati City to Balintawak, Quezon City
- 6-lane (2x3 lanes) fully elevated expressway with a length of 14.8 kilometer
- With 8 interchanges/ramps:
- Buendia
- Plaza Dilao
- E. Rodriguez
- Sgt. Rivera
- Pres. Quirino
- Aurora Blvd.
- Quezon Ave.
- Balintawak
- Alignment:
- OsmeƱa Highway
- Pres. Quirino to Plaza Dilao
- V. Mapa, N. Domingo in Sta. Mesa
- G. Araneta Ave. crosses Aurora Blvd., E. Rodriguez and Quezon Ave.
- Sgt. E. Rivera
- A.Bonifacio towards Balintawak
Buendia, Makati City to Balintawak, Quezon City
PROJECT MAP
- IMPLEMENTING AGENCY: Department of Public Works and Highways (DPWH) and Toll Regulatory Board (TRB)
- CONTACT PERSON: Efren U. Rabot at +63 920 945 2632 and +63 2 631 4673 loc. 4749
- PROJECT OWNER: Citra Central Expressway Corporation
- CONTACT PERSON: Anna Gamboa at +63 917 840 1373 (CORPCOM)
- CONTRACTOR: D.M. Consunji Inc. (DMCI)
- CONTACT PERSON: Engr. Nilo Rey at +63 906 310 4023
- CONSTRUCTION PERIOD
- Section 1 (Advance Work) - March – April 2014
- Section 1 - April 2014 – December 2015
- Section 2 - April 2014 – June 2017
- Section 3 - April 2014 – December 2015
- Section 4 - April 2014 – June 2017