Magallanes Interchange - Repair, Strengthening, Asphalt Overlay

PROJECT DESCRIPTION
  • Asphalt overlay of the third level flyover (along EDSA) and a second level interchange from abutment to abutment (to be divided by into five (5) stages which will be implemented one (1) stage at a time
  • Removal and replacement of damaged expansion dam
  • Strengthening/retrofitting of the deckslab (soffit) of the second level interchange and the inner lane of the third-level flyover (Pasay-bound)
PROJECT LOCATION

Magallanes, Makati City

PROJECT MAP


  • IMPLEMENTING AGENCY: Department of Public Works and Highways (DPWH) - NCR
  • CONTACT PERSON: Call Reynaldo G. Tagudando at +63 2 304 3700
  • CONTRACTOR: J.D. Legaspi Construction
  • CONSTRUCTION PERIOD
    • Phase 2A: Jan 2014 - May 2015
    • Phase 2B: Apr 2014 - Oct 2015