PNR North-South Commuter Railway (PNR Clark)

Schedule for CP04 (N1 E&M) is not correct since it has not yet even entered procurement stage.

Malolos-CIA / Solis-Malolos projected operation - December 2024

Solis-Tutuban (November 2025?)

Solis-Blumentritt - August 2026

Blumentritt-Senate/DeptEd - January 2027

Alabang-Calamba - May 2027

Senate/DeptEd-Alabang - May 2028

Complete System - May 2028


Even though Solis-Blumentritt is just 1.1km, that section is still projected to take 4+ years probably due to project complexities (building over LRT station, relocation of Antipolo Street, etc.). Too bad since Blumentritt will be transfer station between NSCR and LRT-1.


The package with the MMSP interoperability is projected to take the longest to complete.


Of course all these dates are subject to change --- allow additional 1 to 2 years to each projected date to accommodate usual delays. Hopefully the entire system is completed by 2030.