The DOTr said the project, which will add four kilometers of railway tracks from Santolan in Pasig City to Masinag in Antipolo City, is already at 61.93% completion rate as of June 2019.
The LRT-2 extension project will feature two stations – the Emerald station, along Marcos highway and adjoining Gil Fernando and Felix Avenues, and the Masinag station, near Sumulong highway in Antipolo City, Rizal.
The DOTr said the building of the elevated viaduct is already 100 percent complete, while the design and build of the two additional stations are currently ongoing.
“The Emerald Station in Marikina is 89.51% complete while the Masinag Station in Antipolo is at 86.86% complete,” the agency added.
Once operational, it is expected to significantly reduce the travel time from Antipolo to Claro M. Recto in Manila to 40 minutes from the current three hours.
The DOTr is targeting to begin its operations by the fourth quarter of 2020.
https://www.untvweb.com/news/dotr-says-construction-of-lrt-2-extension-project-now-61-complete/