Cavite side section (27.5 km)
Project Objective :
P 11.79 Billion
(US$ 262 Million)
(1US$ =Php 45.00)
Laguna side section (14.3 km)
Description :
P 7.9 Billion
(US$ 176 Million)
(1US$ =Php 45.00)
Cavite-Laguna (CALA) Expressway
Project Objective : To ease traffic congestion and support economic development of the Cavite-Laguna (CALA) region
Project Description :
PPP Section
Total Length: 28.90 km (Kawit to Aguinaldo Hway at Silang)
No. of Lanes: 4-lanes
Right-of-Way: 60 meters
Interchanges: 5 grade separated interchanges
Structures: 7,928 meter total length of bridges
ODA Section
Total Length: 18.10 km (Aguinaldo Hway at Silang to Mamplasan)
No. of Lanes: 4-lanes
Right-of-Way: 60 meters
Interchanges: 4 grade separated interchanges
Structures: 7,279 meter total length of bridges
Project Cost : P 35.58 Billion (US$ 827.44 Million)
Project Status : The project was approved by NEDA-ICC Joint TB and CC meeting last July 12, 2012. NEDA Board conditional approval last November 29, 2012 subject to cost reduction
Processes/Activities Timelines
Project Approval January 2013
Start of Bidding Process February 2013 Contract Award August 2013
Design Sept 2013 - Aug. 2014
Construction September 2014 to November 2017
Start of Operation December 2017 Concession Period 35 years (including construction period)
Project Objective :
- To ease traffic congestion and support economic development of the Cavite-Laguna (CALA) region
- Construction of a 27.5 km, 4-lane highway from the terminus of the R-1 Expressway in Kawit, Cavite to Aguinaldo Highway at Silang, Cavite and Laguna
P 11.79 Billion
(US$ 262 Million)
(1US$ =Php 45.00)
Description :
- Construction of a 14.3 km, 4-lane at grade highway, a continuation of CALA Expressway - Cavite side Section to connect with South Luzon Expressway (SLEX) at Sta. Rosa, Laguna
- Provide vital access between various economic zones in Cavite Province and NAIA, Manila Ports, Batangas Port
- Decongest traffic along Cavite roads, particularly Aguinaldo Highway and Governor’s Drive.
- Estimated Cost PhP 7.9 Billion (US$ 262 Million)(1US$ =Php 45.00)
- Proposed PPP Scheme: Type 3 + Type 5
P 7.9 Billion
(US$ 176 Million)
(1US$ =Php 45.00)
Cavite-Laguna (CALA) Expressway
Project Objective : To ease traffic congestion and support economic development of the Cavite-Laguna (CALA) region
Project Description :
PPP Section
Total Length: 28.90 km (Kawit to Aguinaldo Hway at Silang)
No. of Lanes: 4-lanes
Right-of-Way: 60 meters
Interchanges: 5 grade separated interchanges
Structures: 7,928 meter total length of bridges
ODA Section
Total Length: 18.10 km (Aguinaldo Hway at Silang to Mamplasan)
No. of Lanes: 4-lanes
Right-of-Way: 60 meters
Interchanges: 4 grade separated interchanges
Structures: 7,279 meter total length of bridges
Project Cost : P 35.58 Billion (US$ 827.44 Million)
Project Status : The project was approved by NEDA-ICC Joint TB and CC meeting last July 12, 2012. NEDA Board conditional approval last November 29, 2012 subject to cost reduction
Processes/Activities Timelines
Project Approval January 2013
Start of Bidding Process February 2013 Contract Award August 2013
Design Sept 2013 - Aug. 2014
Construction September 2014 to November 2017
Start of Operation December 2017 Concession Period 35 years (including construction period)
No comments:
Post a Comment