Monday, April 2, 2018

Gov't sees 20 MRT trains operating in 6 months

The Department of Transportation (DOTr) sees up to 20 operating trains for the Metro Rail Transit (MRT) in 6 months, Undersecretary for Railways TJ Batan told CNN Philippines New Day.

Batan said they are optimistic of this target with the entry of Japanese rehabilitation service providers in May.

The government announced in November 2017 that Japanese firm Sumitomo Corporation and technical partner Mitsubishi Industries would be returning as service provider.

Batan added they are "on track" with their deliverables as they achieved 10 operational trains by early March and 15 trains after the Holy Week.

"After our Holy Week general maintenance as of this morning, we are on track to deploying 15 trains for today," he said. As of 2:18 p.m. there are 15 trains running.

DOTr last fielded 15 trains on January 5.

The MRT as well as Light Railway Train Lines 1 and 2 were shut down during the Holy Week break for general maintenance.

Authorities will discuss with Japanese government representatives this week on the specifics of the MRT rehabilitation program.

"We are on track to gradually restoring MRT to the service our passengers deserve," Batan said.

The MRT runs on EDSA from North Avenue in Quezon City to Taft Avenue in Pasay City.

MRT trains back in operation after maintenance ops during Holy Week break

Commuters began forming the usual lines at the North Avenue station of the Metro Rail Transit 3 as early as before 6 a.m. Monday, after the train system underwent repairs and maintenance over the Holy Week break.

According to a report on Unang Balita by Bam Alegre, some 15 train sets, two spare cars, and wayside signalling components used to detect trains and avoid collisions were repaired and restored during the annual maintenance schedule of the MRT-3 this Holy Week.

Rails, sweepers, barricades, station facilities, and other components of the train service were also maintained.

The Department of Transportation (DOTr) said five trains will be "resurrected" for service on the main line.

As of 8 a.m., there were 14 trains running, DOTr said in a tweet.

15 trains running as MRT-3 resumes operations after Holy Week break–Transport dept

THE Department of Transportation (DOTr) said it has achieved its target to run 15 Metro Rail Transit-3 trains on Monday, as the railway system resumed its operations after the Holy Week break.

As of 3 p.m. on Monday, the MRT-3 said it has 15 operational trains with arrival intervals of six minutes.

“We’re now running 15 trains… We last fielded 15 operational trains on January 5, 2018,” DOTr- MRT-3 media relations officer Aly Narvaez told reporters.

On Sunday, the DOTr said that it has completed restoration of 47 cars of the MRT-3, equivalent to 15 trains plus two spare light rail vehicles.


The DOTr said that it was currently working to have 16 trains for deployment. REICELENE JOY N. IGNACIO

Connector road construction begins June

NLEX Corp. is set to start the construction by June  the P23-billion connector road project linking the North Luzon Expressway (NLEX) and the South Luzon Expressway (SLEX), according to Rodrigo Franco,  NLEX Corp. president and chief executive officer.

Once completed by 2021, the connector road will  reduce travel time between the two expressways from two hours to 20 minutes. It will also help improved connectivity between the Ninoy Aquino International Airport and the Clark International Airport.

Right-of-way (ROW) acquisition proceedings are still being undertaken by the Department of Public Works and Highways (DPWH), Franco said.

NLEX Corp.’s parent firm Metro Pacific Tollways Corp. (MPTC) will raise funds to finance the construction.

“When the connector road starts, we need additional funding,” Franco said.

The initial part of the construction will be financed by the funds to be raised from a retail bond issuance.

MPTC will raise additional funds towards the end of the year or early next year, depending  on the connector’s  scheduled construction, Franco said.

The company plans a  P25-billion bonds issuance of which an initial  P4 billion to P6 billion will be launched soon to refinance maturing debts and other projects.

MPTC is optimistic government will be able to settle the issue on the five-kilometer common alignment connecting MPTC’s  NLEX-SLEX connector road to the San Miguel Corp. (SMC) ’s P26.5-billion Metro Manila Skyway Stage 3.

Franco said  discussions are ongoing between NLEX and the DPWH.

“I’ve seen a report…  (SMC is) planning a… change in the alignment in Skyway  but we’re taking the view that our contract  is with the  government and the government will provide us the  connection to the Skyway,” Franco said.

“We believe the government will be taking an active role in making sure (the connector road and the Skyway) will be connected,” he added.

Based on original proposal, the two expressways will be connected in Plaza Dilao and PUP Sta. Mesa.

“It is important to us to connect originally in Sta. Mesa,” Franco added.

Under the contract, NLEX Corp. will construct, operate and maintain the P23-billion unsolicited project.

The connector road is an eight-kilometer four-lane elevated expressway over the Philippine National Railway ROW from the C3/5th avenue interchange in Caloocan City to PUP Sta. Mesa, Manila.

15 MRT trains to run starting Monday

FIFTEEN train sets—or about 75 percent of its rated maximum capacity—should run on the tracks of the Metro Rail Transit (MRT) Line 3 starting today, Monday, after the government successfully restored 45 train cars over the Holy Week break.

Aly V. Narvaez, a spokesman of the MRT 3, said the government hopes to meet its target of mounting 15 train sets on the railway line today to provide a better commuting experience to the riders of the facility.

“We have restored 45 cars already, but we have yet to assess if we can already deploy the 15 train sets tomorrow [Monday],” she told the BusinessMirror last Sunday afternoon.

Narvaez explained that the government still needs to do a safety audit on the light rail vehicles restored last Sunday night. But she assured that there should be at least 13 trains ready for revenue operations.

“They will undergo safety checks and test runs tonight [Sunday] to ensure that they are in good condition for revenue operations, especially when some of these cars were down for quite some time,” she said.

Before the Holy Week—when train operators usually do their full-blast maintenance work for their train systems—there were 13 trains operating.

“If all cars are okay after the checks, if not 15, we could deploy about 13 to 14 train sets, and usually leave a spare train in case of removals,” Narvaez said.

But given the influx of commuters on Monday, the government will “definitely have to deploy 15 trains” should all 45 cars pass all operational checks.

“We have already checked them earlier today [Sunday], but we have to redo the checks tonight and early on Monday morning. This is how thorough the preparatory works are, since they’re part of the safety measures,” Narvaez said.

The government currently maintains the railway facility through a “maintenance transition team,” which it deployed last year, after firing its upkeep contractor for its alleged mishandling of its contract.

The MRT has been a huge headache for both commuters and the government since 2012, when major issues sprouted out of poor maintenance works done by contractors.

And the government is hell-bent on addressing the issues plaguing the facility—a privately owned, but government-operated infrastructure—soon.

Narvaez said the audit being done by the Japan International Cooperation Agency (Jica) would soon be completed. This will determine the possible steps on how to move forward with the chronic problems of the facility.

“Our direction is still to bid out the rehabilitation and maintenance of MRT in partnership with Japan. Next steps will be identified after the audit,” she said. “The Jica audit is almost complete; there are some data that just need validation.”

The Philippine government is seeking to be granted an official development assistance financing package for the overhaul and maintenance of the MRT 3.

The government is currently directly engaging Sumitomo Corp. and its technical partner Mitsubishi Heavy Industries for the upkeep of the MRT 3. The two companies designed, built and maintained the MRT 3 in its first 12 years of operations. The Japanese maintenance provider will be mobilized for three years to May 2021.

Sumitomo’s maintenance contract was terminated in 2012, after the previous government decided to take over the component despite contrary provisions in the build-lease-transfer contract with MRT Corp.

The government is also considering the multibillion-peso unsolicited proposal of Metro Pacific Investments Corp. for the MRT 3.

The group submitted in 2017 a P30-billion unsolicited proposal that involves the expansion of the capacity of the railway system by adding more coaches to each train, allowing it to carry more cars at faster intervals.

It would double the capacity of the line to 700,000 passengers a day, from the current 350,000 passengers daily. The multimillion-dollar expansion is deemed as an all-encompassing deal, including the improvement of the reliability of rolling stock, the upgrading of power supply, the upgrading of stations and the replacement of rails, which will allow the company to operate the new trains purchased by the government from Chinese train manufacturer Dalian.

Unsolicited proposals are required, under the law, to be subjected to a Swiss challenge, wherein other groups can offer a similar proposal, and the original proponent can present a counter offer.

The government awarded the original-proponent status to the company last year.

The unsolicited proposal for the MRT mimicked the same provisions under its concession agreement for the Light Rail Transit 1 operations and modernization deal, which it bagged in 2014 via the Public-Private Partnership Program.

It means that, instead of having a different operator and maintenance provider, the group will be the one to do both, something that the SobrepeƱa group has been pushing for since the government forcibly took over the upkeep of the facility in 2012.

Sunday, April 1, 2018

15 MRT-3 trains, two spares ready to run on Monday, says transport official

THE Department of Transportation (DOTr) has completed restoring 47 cars of the Metro Rail Transit-3 (MRT-3), equivalent to 15 trains plus two spare light rail vehicles, an official said.

“We have restored 47 cars. That’s equivalent to 15 trains plus two spare light rail vehicles (LRVs). We are now working on 16….These cars are still undergoing safety checks and test runs,” DOTr-MRT3 media relations officer Aly Narvaez told reporters on Sunday.

“They have to pass the necessary safety checks and test runs before we deploy them. We’ll know the final number of available trains for deployment on Monday early morning,” Narvaez added.

The DOTr said that it was targeting to deliver 15 trains by April 2, when the MRT-3 would resume operations after the Holy Week break.


“Just four more cars to restore before we reach our target of 15 operational trains at peak hours after Holy Week,” the DOTr-MRT3 said.

It said that there were 41 serviceable cars as of March 28.

The DOTr-MRT-3 said the interval between trains would range from four to five minutes. REICELENE JOY N. IGNACIO

Construction of NLEX-SLEX Connector Road to start by July

Back in July 2016, NLEX Corporation secured a P23.2-billion deal to build, operate, and maintain the NLEX-SLEX Connector Road

The tollways unit of Manuel Pangilinan-led Metro Pacific Investments Corporation (MPIC) will start building a toll road connecting the North Luzon Expressway (NLEX) and the South Luzon Expressway (SLEX) by July this year.

"By June or July, we should be mobilizing by that date," Rodrigo Franco, president and chief executive officer of NLEX Corporation, told reporters on the sidelines of an event in Quezon City.

It was in July 2016 when NLEX Corporation secured a P23.2-billion deal to build, operate, and maintain the NLEX-SLEX Connector Road – an unsolicited proposal to the Department of Public Works and Highways (DPWH).

The NLEX-SLEX Connector Road would link C3 in Caloocan City to the Polytechnic University of the Philippines (PUP) campus in Sta Mesa, Manila.

Some segments, according to the Public-Private Partnership (PPP) Center, would run above the lines of the Philippine National Railways (PNR).

"When the connector project starts, we will need additional funding," Franco said.

NLEX Corporation had earmarked P19 billion this year for the construction of the NLEX-SLEX Connector Road and the Harbor Link Segment 10.

Proposed in 2010

The Pangilinan-led firm first submitted an unsolicited proposal in 2010 for the connector road.

On January 21, 2014, NLEX Corporation signed a joint venture agreement with state-run Philippine National Construction Corporation (PNCC) – the holder of the NLEX franchise – to build that road.

But months later, the Department of Justice (DOJ) said that the National Economic and Development Authority (NEDA) Board approval of the agreement was "without factual basis or justification."

The connector road proposal was again subjected to review by the NEDA Board.

In February 2015, the NEDA Board ruled that Manila North Tollways Corporation's offer should be bid out through a Swiss challenge.

A Swiss challenge is the course the government takes when dealing with unsolicited proposals. It requires an invitation to make competing offers while giving the original proponent the right to match them. (READ: EXPLAINER: Not all projects are eligible for a Swiss challenge)

Because of the changes in the mode of implementation and right-of-way acquisition, the expected start of commercial operations of the NLEX-SLEX Connector Road has been moved to February 2022.

Thursday, March 29, 2018

DOTr to get Dalian trains study from audit firm next week

Though the audit report on the Dalian trains is expected to be released to the Department of Transportation (DOTr) after the Lenten break, the public will have to wait a little longer to see if they can finally get to ride the new coaches which are now gathering dust at the Metro Rail Transit 3 (MRT 3) depot.

Transportation Secretary Arthur Tugade said on Wednesday that the report on the 48 China-made trains worth P3.8 billion would be submitted to him next week.

Earlier, the DOTr said that independent audit firm TUV Rheinland has yet to conclude its study on the trains since there was still a need to gather “additional information on design and validation evidence,” as well as to conduct further “type and routine tests.”

One of its recommended tests deals with the trains’ weight. The DOTr has yet to schedule the weight tests.

While all the Dalian trains bought by the Aquino government were delivered in January last year, these have yet to be rolled out due to supposed safety and compatibility issues with the MRT 3’s current rolling stock.



Read more: http://newsinfo.inquirer.net/978907/dotr-to-get-dalian-trains-study-from-audit-firm-next-week#ixzz5BR4fIicx
Follow us: @inquirerdotnet on Twitter | inquirerdotnet on Facebook

Tuesday, March 27, 2018

Traffic Calvary: MMDA to close Commonwealth-Philcoa U-turn on Holy Thursday

MMDA General Manager Jojo Garcia says affected motorists will have to go around the Quezon Memorial Elliptical Road to head to Commonwealth Avenue eastbound

REROUTING PLAN. The MMDA releases a rerouting plan ahead of the MRT7 construction along Commonwealth-Philcoa area in Quezon City. Photo courtesy of MMDA
Motorists who travel along the area of Commonwealth Avenue and the Quezon Memorial Elliptical area in Quezon City, brace yourself.

Expect the already heavy traffic in the vicinity to get even heavier with the closure of the U-turn slot along the Commonwealth-Philippine Coconut Authority (Philcoa) vicinity beginning Holy Thursday, March 29, to give way to Metro Rail Transit Line 7 (MRT7) construction.

In a press briefing on Monday, March 26, Metropolitan Manila Development Authority (MMDA) General Manager Jojo Garcia said affected motorists, those who take the U-turn at the end of Commonwealth Avenue, will instead have to go around the entire Elliptical Road to return to Commonwealth Avenue.

Garcia said the U-turn slot will reopen August 2018.

But the closure of the U-turn is not the only "Kalbaryo" for motorists, the MMDA said private contractors will also occupy two inner lanes of Commonwealth Avenue-Philcoa area on both directions.

As a palliative, the MMDA said they would remove obstructions on the outer portions of Commonwealth Avenue to "widen" the remaining lanes.

Garcia also said that they will install plastic barriers along Maharlika Street to serve as separators to prevent vehicles going to Commonwealth Avenue from swerving into other lanes.

In the rerouting plan, MMDA said motorists going to Visayas and North Avenue should stay on the left, while those going to Commonwealth must stay on the right lane:

  • From Masaya Street
    • To Commonwealth Avenue
      • Right to Maharlika Street
      • Right to Elliptical Road
      • Right to Commonwealth Avenue
    • To Visayas, North Avenue
      • Left to Maharlika Street
      • Right to Mayaman Street
      • Right to Kalayaan Avenue
      • Right to Elliptical Road
  • From Elliptical-Kalayaan Junction
    • To Commonwealth Avenue
      • Stay at right lanes
    • To Visayas, North Avenue
      • Stay at left lanes
  • Commonwealth Avenue (Southbound)
    • To Commonwealth Avenue
      • Take Elliptical Road


According to the MMDA Traffic Engineering Center, at least 2,125 vehicles traverse to portion of Elliptical Road to Visayas and North Avenue during the usual morning rush hour.

Some 4,120 vehicles from Elliptical Road turn to Commonwealth Avenue during the same timeframe.

Diversified conglomerate San Miguel Corporation (SMC) broke ground for the $1.6-billion MRT7 project in April 2016. The 23-kilometer railway system, which will run from North Avenue in Quezon City to San Jose del Monte City, is expected to be completed by 2020.

It will have 14 stations which will take 30 minutes to travel end-to-end: North Avenue, Quezon Memorial, University Avenue, Tandang Sora, Don Antonio, Batasan, Manggahan, DoƱa Carmen, Regalado Highway, Mindanao Avenue, Quirino, Sacred Heart, Tala, and San Jose del Monte.

The MRT7 will also connect to the existing MRT3 and Light Rail Transit Line 1 (LRT1), with the common station to be located between SM North EDSA and TriNoma malls in Quezon City.

U-turn slot along Commonwealth to be closed for MRT-7 construction

The Metropolitan Manila Development Authority (MMDA) on Monday warned motorists passing along Commonwealth Avenue that one of the U-turn slots located in the area would be closed starting Thursday.

Jojo Garcia, acting General Manager of the MMDA, said that the U-turn slot in Commonwealth Avenue-Philcoa would be closed in preparation for the construction of the tunnel guide way for MRT-7.

He said that the construction would take up two inner lanes of both directions in the Commonwealth Avenue area.

Despite this, Garcia said that the MMDA and the private contractors have agreed to widen the remaining lanes by removing the plastic barriers in the affected area.

“We are glad private contractors are coordinating with us to make the necessary adjustments to ease the expected traffic build-up in the area caused by the ongoing MRT 7 construction,” said Garcia in a statement.

He then advised the motorists to use the Elliptical Road in order to go back to Commonwealth Avenue-eastbound.

“Vehicles traversing Elliptical Road going to Visayas and North Avenue area should stay at the left lane while vehicles going to Commonwealth Avenue should stay at the right lane,” he said.

The MRT-7, once finished, would have an elevated transit line spanning 22.8 kilometers from San Jose del Monte, Bulacan to North Avenue, Quezon City. /je



Read more: http://newsinfo.inquirer.net/978223/u-turn-slot-commonwealth-philcoa-mmda-mrt-7-construction-tunnel-motorist-closed#ixzz5BWUKHDBv
Follow us: @inquirerdotnet on Twitter | inquirerdotnet on Facebook